Hi experts !
I'd like informations about summarization of projects.
I have few projects. in the projects, there are internal processing which made costs with the activity type.
when i make a summarization of projects, I have the cost of the activity type which correspond to my hierarchy but i'd like to see in a report the number of hours, for example, and not only the costs. but how can i have this result ?
The report of summarization concern just costs. A project manager can have to know the number of hours he is in charge.
thanks for help
Benny
Hai benny
In SAP standard transaction available like CN41N , CN41 where u can get the required one by selecting the proper fields and u can save the layout as per requirement and use the same for same kind of reports.
Hope the point is clear.
ENJOY SAP PS.Award points.
Regards
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai Benny
U can have the cost information with respect to Project responsible / Projects / Controlling area / etc in CN41 or S_ALR_8701351 . If any of these tranasactions is called - u will get a screen in these - under EDIT tab -
Select DYNAMIC SELECTIONS -Shift+F4 - (according to ur requirement like Reports belong to one controlling area and its costs or Project Responsible and his planned or actual costs) give inputs to the fields and execute.
Based on ur field selection - u can get reports as per Standard SAP.
Awards Points if helpful.
Regards
PP
Hai Benny
U can have the cost information with respect to Project responsible / Projects / Controlling area / etc in CN41 or S_ALR_8701351 . If any of these tranasactions is called - u will get a screen in these - under EDIT tab -
Select DYNAMIC SELECTIONS -Shift+F4 - (according to ur requirement like Reports belong to one controlling area and its costs or Project Responsible and his planned or actual costs) give inputs to the fields and execute.
Based on ur field selection - u can get reports as per Standard SAP.
Awards Points if helpful.
Regards
PP
Hi Benny,
What I can make out of your query is you want the total up of hours for a particular plant or profit centre or controlling area right? if yes then it is only possible with using CATS ask your CATS specialist they can provide you the total hours charged for the particular area. More over the project summerization is more or less dedicated for cost summerization not for hours thats why it has been placed under financial folder. I have just implemented the project summerization in our project but didn't see any field like hours...yes of course you can get the cost against activity type but not against total hoursin project summerization....just check if class type 13 or 21 they might have hours field as charcteristics...
Good Luck
Chetan