Urgent assistance would be greatly appreciated.

I am having problems with the working hours calculation in network activities as it is including non working days from the factory calendar that has been pulled through from the work centre.

Example:

Fixed duration of 4 months (March to June 2007) for 1 person at 80% utilisation should calculate to 531.2 hours work time based on factory calandar GB which gives 83 working days. SAP is calculating 768 hours which relates to 120 working days which includes the 37 non working days in the period.

Any ideas on how I can get the calculation to exclude the non working days would be very welcome.

Thanks in anticipation

Dave Chapman

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hai Dave

The first preference for the activity will be the calendar entered and the time entered in the Standard available capacity and corresponding breaks in the workcenter then it will prefer Calendar from Project definition.

The calendar(GB) which u chooses in 5 working days in a week. check whether u r maintaing the same calendar which is in Project definition and in work center and the time in the work center.

ENJOY SAP PS. AWARD POINTS IF HELPFUL.

Regards

PP

Former Member
0 Kudos

Thanks PP

Calendar GB maintained in both project definition and work centre. Time for working day also in work centre however still calculating work with a 7 day week. Any other ideas would be thankfully received.

Regards

Dave

Former Member
0 Kudos

Hi,

Please check the factory calendar assigned to project profile as most of the factory calendar there is five working days.

Go to the transaction SCAL & check the working days of factory calendar. Hope this will help you.

Regards,

Rakesh

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Dave

Your problem seems to be with the calender GB. Use transaction SCAL, change factory calender, edit GB, check how many days are assigned as working days. Uncheck Sat & Sun and public holidays if they are assigned. Hope this solves your issue.

Regards

Renjith

Former Member
0 Kudos

Hi,

Is your factory calendar issues solve or not..

Regards,

Rakesh

Former Member
0 Kudos

Hi

Problem was not in the factory calendar config after all but the SAP calculation routine. ABAP friend assisted as the code needed to be modified so that functional module COPF_DETERMINE_DURATION was taken into account.

Thanks

Dave

Former Member
0 Kudos

Dear Dave,

If you manintained the same factory calendar in both project profile and the work center, then you please check in your workforce planning (tcode cmp2) for the network activities.

I hope you might have entered time booking for that person in holidays also. When you do check availability in workforce planning, you will come to know the no.of holidays and no.of working hours to that person.

Based on the availability of hours to that person book your time and then calculate the capacity at activities level.

Hope this may help you.

All the best!!