Hi gurus,my scenario is price for a material is 100% if its raise without reference to contract,but if it is with reference to contract price should be only 50%.

kindly let me know the solution.

Thanks&regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI try with following it may help you,

While creating condition table pick Sales document and Material and try to process

Answers (3)

Answers (3)

Former Member
0 Kudos

You require to configure Down Payment for 50% value.

<b>How Down Payments Are Configured</b>

The following Customizing settings have to be made for down payment processing:

Settings for the billing plan - To activate the billing plan function, maintain the materials, for which you wish to process down payments, with item category group 0005 (milestone billing). This gives the item type TAO via item type determination. The item type TAO calls up the billing plan function.

You need to implement the following activities in the billing plan for down payments:

Maintain deadline category - This determines the billing rule (percentage or value down payment) for the down payment request. The system assigns billing type FAZ (payment request) defined in the standard system with billing category P. (For the billing type FAZ there is the cancellation billing document type FAS in the standard system).

Maintain the deadline proposal - Use the down payments that are due for the proposed deadlines.

Maintaining a Pricing Procedure with the Condition Type AZWR:

In the standard system the condition type AZWR is delivered for the down payment value already provided but which has not yet been calculated. You must include this condition type in the relevant pricing procedure before output tax.

Enter condition 2 (item with pricing) and the calculation formula 48 (down payment clearing value must not be bigger than the item value) for the condition type AZWR.

Before the condition AZWR you can create a subtotal with the base value calculation formula 2 (net value). If the condition AZWR is changed manually, you can get information on the original system proposal from the subtotal.

Maintain the printing indicator - The pricing procedure can not be marked as a transaction-specific pricing procedure (field Spec.proc.) The condition type AZWR has the calculation type B (fixed amount) and the condition category E (down payment request / clearing).

Maintaining the Billing Document - In the standard system there is the billing type FAZ (down payment request) and the billing type FAS for canceling . The down payment is controlled using the billing category P of the billing type. A billing type becomes a down payment request when the billing category P is assigned. You have to maintain blocking reason 02 (complete confirmation missing) for the billing documents and assign it to billing type FAZ.

Copying control - Copying requirement 20 must be entered in copying control at item level for the down payment request. In the standard system the order type TA for copying control is set up according to the billing type FAZ for the item category TAO.

Copying requirement 23 must be entered in copying control at item level for down payment clearing. In the standard system the order type TA for copying control is set up according to the billing type F2 for the item category TAO.

Financial Accounting settings - A prerequisite for down payment processing is that the account is assigned to the underlying sales document. To do this, change the field status settings in Customizing as follows:

Set reconciliation accounts (transaction OBXR) - For the `received down payments' and `down payment requests' from

the G/L accounts you have selected, you should assign the field status definition G031.

Maintain accounting configuration (transaction OBXB) - For the down payments (posting key ANZ in the standard system) and the output tax clearing (posting key MVA in the standard system), you must maintain the posting key.

You must also carry out a G/L account number assignment for the tax account.

Maintain the posting key (transaction OB41) - For posting key 19, set the sales order as an optional field !!!

Maintain the field status definition (transaction OB14) - For field status variant 0001, field status group G031, set the

sales order as an optional field !!!

Assign the company code to the field status variants (transaction OBC5)

Regards,

Rajesh Banka

Reward suitable points.

  • How to give points: Mark your thread as a question while creating it. In the answers you get, you can assign the points by clicking on the stars to the left. You also get a point yourself for rewarding (one per thread).

Former Member
0 Kudos

hi,

The document pricing procedure for all the contract documents is by default different from others. Pls check out in the documents WK1 and WK2.

Here, you assign the pricing procedure which calculates the 50% pricing for the product(through condition technique maintain the 50% price condition record) and assign sales area, CUpp, DOpp(of contract document).

Maintain B = Pricing elements unchanged from contract to release order. Maintain release order as a different order document type. Use it only for release orders.(Not for normal orders).

Here, the 50% price calculated in the contract document type is copied into the release order.

Reward points.

Ram kiran

Former Member
0 Kudos

Dear Ravishankar,

Please follow these steps..

1 Takes sales document as one field when you are choosing Table

2.Maintain Record for material 100%

3.Maintain Material Price for contract taking One field as Sales document as 50%

Example of Records

Material Price

Nokia N70 15000

Sales document Material Price

QT Nokia N70 7500

I think this will solve your problem

Reward suitable points.

  • How to give points: Mark your thread as a question while creating it. In the answers you get, you can assign the points by clicking on the stars to the left. You also get a point yourself for rewarding (one per thread).

Regards

MBS