cancel
Showing results for 
Search instead for 
Did you mean: 

Follow on document display shows Release date instead PR Creation date

Former Member
0 Kudos

Hi All,

We have implemented ver 5.0 with ECC 6.0 as backend.

After PR creation in ECC, in check status display of SC, the follow on document shows the PR release date as the Creation date.

Is this standard SAP?

if not is there any option to control this?

ideally the display should show the PR creation date.

Any inputs will be appreciated.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

It is standard SAP. Better to cross-chek with SAP by raising a Customer OSS Message as well.

I guess, For this you need to modify the standard HTML Templates in SRM, by Which the required Date can be displayed in the SC check status transaction.

See two related SAP OSS Notes, which will give you some Idea where you need to modify the HTML Template to display the required date in your case.

Note 884904 - Service performance date not displayed

Note 814318 - Accessibility in the shopping cart

Do let me know.

Regards

- Atul

Former Member
0 Kudos

Hi Atul,

Thanks for your inputs.

What i meant what was in the follow on document(graphic display) history.

Is there any option via config, where in the system should pick field BADAT from EBAN instead of FRGDT(release date) for the PR Creation date.

As you must be aware, SAP defaults the delivery date as the release date in PR.

Any inputs.

rgds,

Biswah

Former Member
0 Kudos

Hi

I am afraid., .. Only by Modification at the SRM - HTML Template level, this can be possible.. not through config.. as such..

<u>Please go through the SAP OSS Notes as well before going for any modifications in SAP code</u>

<b>SAP OSS Notes -></b>

Note 494036 BBP_GET_STATUS, BBP_STATUS_READ: several problems in backend

Note 540339 Purchase requisitions are transferred incorrectly

Note 436223 Change of the table calls in function module BBP_STATUS_READ

Note 1015447 Pricing simulation date (PRSDT) is wrong in ME57

Note 422923 ME51: Release date for new items in purchase requisition

Note 868013 ME51N: PR release date not calculated correctly for SKU

Note 574515 BAPI_REQUISITION_CREATE, impossible to set Release date

Note 726708 Requirement dates of the components in SC orders V

Note 685327 Release date at item level for purchase requisition in ME52N

Note 523604 Requirement dates of the components in SC orders IV

Note 366843 Requirement dates of components for SC stock III

Note 88629 Changeability of the release date

Do let me know.

Regards

- Atul

Former Member
0 Kudos

Hi Atul,

We have implemented classic scenario SRM 5.5 verison in which when we do describe requirement and limit Shopping cart.When the shopping cart in approved PR is getting generated in backend.From PR furthur procurement process is completed in R/3.

Problem is R/3 has got some Value based contract or schedulling agreement which is tied up to a some vendor for services ,those vendor are given as source of supply or preffered vendor list for the SC's in SRM.When we select the vendor in Shopping cart who has got value contract or schedulling agreement where we can see that he has got a contract in r/3. The agreement number or value contract number is not getting displayed in the agreement field in PR in backend.Please advice how to solve the problem.

regards

Harinath