Hi to all,
can any one please explain the difference between snp planned order and pp/ds planned order. I am relatively new to this area
The primary differences are as below.
1. The master data for SNP Planned Order is SNP PPM/PDS where the minimum duration for an operation is a day. So it is used for rough cut capacity planning.
The master data for PPDS Planned Order is a PPDS PPM/PDS where operations are down to minute and second level. Moreover sequence dependent operation planning is possible in PPDS Planned Orders. It is for detailed capacity planning.
2. SNP Planned Orders are created in SNP while PPDS Planned Orders are created in PPDS or when transferred from ERP to APO.
3. SNP Planned Order need to be converted to a PPDS Planned Order before it can be used in the Execution System (ERP) for further processing - like conversion to Production Order. Moreover the category types of the orders are different in APO (EE for SNP and AI for PPDS).
Hope this helps.
Somnath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.