Hello,

We are running SCM 4.1 SP12. Apparently as of SP12 there is new funtionality which allows optimizer runs to use parallelism so they can complete faster. I have created an seperate instance on SNP. It's been registered and shows up in OPT09.

Can someone tell me how to make optimizer runs either spawn a second process or use the second exe I've supplied?

Thanks in advance!

Ben

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

System will decide as per the available server load

You will not have any control on it to choose the server when you use parralel processing

Former Member
0 Kudos

I'm sorry perhaps I was not clear in my question. Essentially, I have created a second instance of the optimizer, but the optimizer runs do not use the second instance which I've provided.

In addition, I've created a parallel profile and assgined it to the default SNP Optimizer profile.

Thanks,

Ben