Activiy Confirmation on GR

Former Member
0 Kudos

I have a Project Network where Materials are attached to some of the activities.

I have a requirement that confirmation of these activities should not be allowed unless all the attached materials are received and/or issued to project.

Can anybody help?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Tushar

Pl try ... set USER STATUS for activities..

Enjoy SAP...

Regards

Sudhakar