I have a Project Network where Materials are attached to some of the activities.
I have a requirement that confirmation of these activities should not be allowed unless all the attached materials are received and/or issued to project.
Can anybody help?
Hi Tushar
Pl try ... set USER STATUS for activities..
Enjoy SAP...
Regards
Sudhakar