cancel
Showing results for 
Search instead for 
Did you mean: 

error during multilevel controlling

Former Member
0 Kudos

I am trying to perform a multilevel controlling. After marking flag to transfer I am getting the following error:

"There is no internal order for project xxxxxxxx". The WBS element is also not created. I am using auto mode for multilevel controlling.

Waiting for your feedback.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi, Anantharam

How can you work on multilevel controlling? Which document are you refering to?

Thanks.

Former Member
0 Kudos

You can check in help.sap.com

Pre-requisities:

1) accounting integration should be checked for the project type

2) Make settings in the ERP system (the system in which you need to reflect the cProjects as PS project)

In case you are not able to do the settings, pl. let me know and I would send you some documents

Former Member
0 Kudos

Hi Anantharam,

I am working on a requirement to get Cost/Revenue Rates from ECC6.0 to cProjects , I know the standard configuration can replicate data from cProjects to ECC6.0 , I need to know do we have anything from the other way round,

can you please send me the document which you have for cProjects Accounting Integration

to email-id kumar.sap@gmail.com

Thanks

Praveen

Former Member
0 Kudos

solved on own

former_member214272
Contributor
0 Kudos

Hi Anarharam,

I am facing the same problem, during multilevel contolling.

Can you guide me for solving the error or if you have any document relative to this please send me at suniljawalkar@hotmail.com

thanks

sunil jawalkar