Hello SAP Gurus,
In a project there are 3 WBS elements. Under each WBS there is a WBS element, which takes care of Procurement. I would like see the total procurement cost (sum of these 3 WBS elem)?
Using Summarization Report can it be achieved? If yes, how we can do that?
Help is greatly appreciated.
Best Regards,
Venkat
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The detail requirements can be obtained from reports (S_ALR_87013543/42/45 ). Cost details can be obtained from Project info systems also. (CN41)
Hope this wil suffice you.