on 07-02-2007 8:00 AM
Hi,
I am looking for a user-exit/enhancement that is triggered when saving/updating a project in PS (release 4.6C). I already looked in the CNEX* range of user-exits, but couldn't find anything that seems usable. The purpose of the user-exit is to be able to change the status of the sales order item that triggered the creation of the project (assembly processing).
Regards,
Paul
Message was edited by:
P. Hensgens
Hi,
There is generally no user-exit or BaDi for the CJ20N. If the settings of 'Option' of project builder does not have the required functionalities, the 'substituation' functionality may be the last possibility to apply the customer own logic.
Customizing path: Structures -> Operative Structures -> Work Breakdown Structure (WBS) -> Maintain Substitutions
Thanks,
Anitha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i haven't used thsi so far but perhaps the BAdI [PROJECTDEF_UPDATE] is the solution for you.
Regards
Bernd
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.