GOA distribution-Issue with IDOC

Former Member
0 Kudos

Hi Everyone,

System : ECC 6.0, SRM 5.0(Package : SAPKIBK007)

GOA created for a material with a plant specific price of $10 for plant ABC and a plant independent price of $12. When we distribute to the plant ABC, a contract is being created in ECC using the message type BLAORD 03 and COND_A. In this above scenario we got one IDOC with BLAORD 03 and 2 IDOCS with COND_A.

1. BLAORD 03 IDOC has plant ABC and a plant specific price($10). This IDOC has been processed successfully. and created a contract for plant ABC with a wrong price of @ $12(plant independent price).

2. The first COND_A IDOC has a price of $12.

3. The second COND_A IDOC has a price of $10.

How can we correct this situation so that the contract will be created with the correct price($10). Is there any problem with the IDOC structure?

Thanks

Aneesh.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Solved it on my own.

Former Member
0 Kudos

Hi

Seems to be a bug in the system.

<b>Please go through the following</b> ->

Note 976264 Archiving enhancements in purchasing for ERP 2005

Note 840355 ADIP: Wrong Purchasing info record category

<b>Related links -></b>

Hope this will help.