Hi everyone,

I want to know the process for stock transfer between plant to plant in same company code.

Regards

Prabudh

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

Visit help.sap.com at http://help.sap.com/bp_bblibrary/600/BBlibrary_start.htm and download J51 Internal Procurement document it contains Config. Guide & Business Process.

Regards

Mahendra

Former Member
0 Kudos

Whenever you need to transfer the materials from one plant to another plant belonging to one company or belonging to two company code stock transfer order is raised by the delivering company.

STO:

Transfer of goods from one location to another location,it may be between plants within the same company code or in different company code's plants.

within the company code,bet plants, receiving plant will raise the STO in Supplying/issuing plant-ME21n,

Supplying plant will deliver the goods to receiving plants , then we need to pick n post the Goods Issue-VL02n, nw when we can observe that the STO qtty will be added into receiving plant and reduced in Delievering plant.

Configure Intercompany Stock Transport Order

Material should exist in both the plants (Delivering & Ordering),

Internal customer should be assaigned to the ordering plant ( MM -> Purchasing -> Purchase Order -> Setup stock transport order -> assign the internal customer to the ordering plant and assign the Sales area of the internal customer.

Assign its Sales area to the delivering plant

Assign the document type and Delivery type NB

Assign the Supplying plant --> Receiving Plant --> NB

Take the delivering plant and assign the sales area.

Vendor master has to be created and assaign the supply source ( Delivering Plant).

Create a puchase order ME21N ---> Save

Delivery VL10 G ---> Calculation rule (appropriate) --> Assaign the purchase order number here anand execute.

Select the Delivery creation line and do the back ground process.

Start the log display and see the delivery document number by the documents button

Goto VL02N --> do picking and PGI --> Then do the MIGO with respect to the delivery docume

Stock transfer B/W plant to plant in the same company code is called intra company stock trasfer orders

Former Member
0 Kudos

http://help.sap.com/bp_bblibrary/500/html/J51_IntProcSTwD_EN_IN.htm

In a company, goods movements do not only occur in the form of goods receipts and goods issues. Depending on the organization of the company (for example, decentralized storage) and its sales policy, internal stock transfers might also be necessary.

The stock transfer with delivery is a plant to plant scenario. You are posting a goods issue in plant BP02 and a goods receipt in plant BP01.

This type of stock transfer can only be carried out from unrestricted-use stock of the issuing plant to unrestricted-use stock of the receiving plant.

You post the placement into storage at the receiving plant in a second step. Only then is the event completed and the transferred quantity part of unrestricted-use stock.

Function List

The following functions are provided to support the J51 building block:

Creating a Planned Independent Requirement

Creating a stock transport order in plant BP01

Generating a delivery in plant BP02

Picking of the material and posting the goods issue in the delivering plant

Posting the goods receipt in the receiving plant

Key Points

The quantity posted from stock is first of all managed as stock in transit of the receiving plant. Only once the goods receipt has been posted is the quantity posted to the unrestricted-use stock of the receiving plant. This enables the quantity "on the road" to be monitored.

The transfer posting is valuated at the valuation price of the material in the issuing plant.

Delivery costs can be entered in the stock transport order.

Regards,

Rajesh Banka

Reward suitable points.

Former Member
0 Kudos

Hi,

STO stands for Stock transport order. This is done to enable the stock Transfer from one plant to another.

Configuration for Stock Transport Order:

- Configure using transaction OMGN.

- Depending upon the sending and receiving plants, maintain sales organization and customer data in customizing.

- Maintain the supplying plant as a vendor and attach the plant to the vendor in the Vendor Master.

- Material type has to be HALB or HAWA.

- Ensure that the company with sales Organization has a plant to take care of stocking.

- The PO used is NB and not Stock Transfer PO.

Configure SD for inter-company billing to enable picking up the pricing procedure for billing.

- Carry Out delivery through process delivery due list and billing through process billing due list.

Otherwise, You need to configure your Stock Transport Order settings for your Cross-Company:

Business Transaction to work.

1. Customer No. for the Goods Receiving Plant - OMGN

2. Availability Check- Checking Rule (if necessary) - OMGN

3. Assign a Delivery Type for the Delivering Plant - OMGN (for Stock Transport Orders, NLCC)

4. PO type (which i belive you have done) - OMGN

5. Assign Vendor No. to the Supplying Plant (done) - VK02

6. Assign Customer No. to the Purchasing Plant for the Inter-Compnay Invoice (but you need to assign this to the Sales Organization pre-assigned to the Purchasing Plant),

IMG-SD-Billing-InterCompany Billing-Define Internal Customer No. by Sales Org

***and by the way for the Invoice to work between Cross-Compnay Plants, you need also to have a Sales Org for the Supplying Plant and a Pricing Determination Procedure.

Reward Points if it helps.

Regards,

Sree