When i do posting of goods, the error is "Mat. KEROSINE is a missing part"

Former Member
0 Kudos

Hi,

When I first time posting the qty for my material (kerosine) it shows the following error.

Help needed to solve this.

-


System Response----


The system could neither determine any MRP controller to notify nor any output type used to send the mail message.

Procedure

Please contact the MRP controller responsible or use the current stock/ requirements list to check for which purpose (production order, reservation, for example) the material KEROSINE is required.

Proceed

Action to be taken by system administrator

If the MRP controller wishes to be informed of missing parts situations via a mail message, you have to complete the following settings in the Customizing system of Inventory Management:

Missing parts check at goods receipt

set message determination

-


Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

HI,

path: ImgMaterial ManagementInventory and physical management--plant parameters.

if you are using an IDES version copy the plant 1000 and change the plant to ur plant and make sure that the missing part field is unchecked and save it

hope this will reslove the problem

reward points if the answer is helpful

REgards,

Murali

Former Member
0 Kudos

Missing parts functionality has been set-up for your system (probably incorrectly)

What should happen with missing parts

Configuration and data set-up to manage missing parts

Open Production/Sales reservations exist in system (because of stock shortage)

Goods receipt arrives and identifies that open documents exist

Message displayed to user posting receipt

Mail message sent to relevant MRP contoller (if set up correctly)

Standard functionality