Hi,

This is reference to the captioned SAP note regarding <b>Background job sched.: using processes that have become free</b>. We are planning to implement the same. We are running on <b>ECC 5.0</b> with Basis Patch Level <b>SAPKB64017</b>.

Have anyone has already implemented the notes? how is the performance ?

Also want to find out what is the implementation procedure. Is it only entering the values to <b>BTCOPTIONS</b> table i.e.

BTCOPTION = BTC_DYNAMICAL_TIME_SDL

VALUE1 = ON

VALUE2 = <any comment>

or anything else need to be done.

One more question, is it implementing this will take away the priority of A-Class Jobs. i.e. a situation might arise when the work process are free, all of them are assigned to some long running C-class Jobs, which might result in delaying the A-class Jobs.

Request your suggestions.

Regards,

Sanujit

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

check my last update

Former Member
0 Kudos

Hi All,

Just to share with all. I have implemeneted the note. The performance has been really good till date. Earlier we used to have a lot of Jobs in waiting. Now a days the queue remains clear all the time.

Thanks all.