Hi,
This is reference to the captioned SAP note regarding <b>Background job sched.: using processes that have become free</b>. We are planning to implement the same. We are running on <b>ECC 5.0</b> with Basis Patch Level <b>SAPKB64017</b>.
Have anyone has already implemented the notes? how is the performance ?
Also want to find out what is the implementation procedure. Is it only entering the values to <b>BTCOPTIONS</b> table i.e.
BTCOPTION = BTC_DYNAMICAL_TIME_SDL
VALUE1 = ON
VALUE2 = <any comment>
or anything else need to be done.
One more question, is it implementing this will take away the priority of A-Class Jobs. i.e. a situation might arise when the work process are free, all of them are assigned to some long running C-class Jobs, which might result in delaying the A-class Jobs.
Request your suggestions.
Regards,
Sanujit
check my last update
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Just to share with all. I have implemeneted the note. The performance has been really good till date. Earlier we used to have a lot of Jobs in waiting. Now a days the queue remains clear all the time.
Thanks all.
Sanujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.