hi

can anyone provide info regarding

testing

how many types of test are there

in which phases(ASAP) they wil be conducted

and on which servers

like unit testing on dev

UAT on QA

etc

thanks in adv

sridhar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Sridhar.,

Testing : the core team members along with endusers will test whether the postings done in SAP is resulting as per the requirements of the organisation. They will test whether the output documents such as purchase order, invoice document are printed in the required format and showing the correct data.

Unit testing is refer to the module which are going to implement. SD, MM, FICO etc. there will be test script based on that testing will be performed.

Integration testing will be cross the modules. MM-SD-FICO for example. Integration testing is also called SIT ( System integration testing)

Testing mathologies and types: there are 6 types of testings:

1. Unit Testing

2. System Testing

3. System Integration security Testing

4. Performance Testing

5. User Acceptance testing

6. Regression Testing

Unit testing is done in bit and pieces. Like e.g. in SD standard order cycle; we do have 1-create order, then 2-delivery, then 3-transfer order, then 4-PGI and then 5-Invoice. So we will be testing 1,2,3,4 and 5 seperately alone one by one using test cases and test data. We will not be looking and checking/testing any integration between order and delivery; delivery and TO; TO and PGI and then invoice.

Whrereas System testing you will be testing the full cycle with it's integration, and you will be testing using test cases which give a full cyclic test from order to invoice.

Security testing you will be testing different roles and functionalities and will check and signoff.

Performance testing is refered to as how much time / second will take to perform some actions, like e.g. PGI. If BPP defination says 5 seconds for PGI then it should be 5 and not 6 second. Usually it is done using software.

Regression testing is reffered to a test which verfies that some new configuration doesnot adversly impact existing functionality. This will be done on each phase of testing.

User Acceptance Testing: Refers to Customer testing. The UAT will be performed through the execution of predefined business scenarios, which combine various business processes. The user test model is comprised of a sub-set of system integration test cases.

We use different software during testing. Most commonly use are

Test Director: which is used to record requirement, preparing test plan and then recording the progress. We will be incorporating defects that are coming during these testings using different test cases.

Mercury Load Runner: is used for performance testing. This is an automatic tool.

What does the following terms means :

- Technical Unit Testing

- Functional Unit Testing

- IntegrationTesting

- Volume Testing

- Parallel Testing?

Technical Unit Testing= Test of some technical development such as a user exit, custom program, or interface. the test usually consists of a test data set that is processed according to the new program. A successful test only proves the developed code works and that it performed the process as as designed.

Functional Unit Testing= Test of configuration, system settings or a custom development (it may follow the technical unit testing) These usually use actual data or data that is masked but essentially the same as a real data set. A successful test shows that the development or configuration works as designed and the data is accurate as a result.

IntegrationTesting= Testing a process, development or configuration within the context of any other functions that the process, development or functionality will touch or integrate . The test should examine all data involved across all modules and any data indirectly affected. A successful test indicates that the processes work as designed and integrate with other functions without causing any problems in any integrated areas.

Volume Testing= testing a full data set that is either actual or masked to insure that the entire volume does cause system problems such as network transmission problems, system resources issues, or any systemic problem, A successful test indicates that the processes will not slow or crash the system due to a full data set being utilized.

Parallel Testing= Testing the new system or processes with a complete data set while running the same processes in the legacy system. A successful test will show identical results when both the legacy system and new system results are compared.

I would also note that when a new implementation is being done you will want to conduct at least one cut over test from the old system to the new and you should probably do several.

What kind of testings that are carried out in testing server?

1. Individual Testing ( Individually which we've created)

2. Regressive Testing ( Entire Process)

3. Integration Testing ( Along with other integrated modules)

The 3 types of testing is as follows:-

1. Unit testing (where an individual process relevant to a SD or MM etc is tested)

2. Integration testing (where a process is tested that cuts across all areas of SAP).

3. Stress testing (where lots of transactions are run to see if the system can handle the data)

Thanks & Regards

Narayana

former_member183879
Active Contributor
0 Kudos

There are various kinds of testing.

Unit testing

Testing the functionality standalone (say in quality client, or in devlpmt client itself). This is done to ensure that the functionality is working fine.

Integration testing

Testing the developed functionality in sync with other functionalities which can influence the developed functionality. This testing is done to do the impact analysis of hte process.

Stress testing

This is done to ensure that the system willnot crash if the number of users are more. This test is done by enabling 100s of users to logon to the system at a predefined point of time and executing transactions of various nature. In some cases, transaction taking long time too.

User Acceptance testing

The tests done by the users after integration testing by the functional consultants is called so. They do this to give a final go ahead on the functionality to be enabled in producn system.

Regression testing

This is done to ensure that the exisitng functionalities are not affected due to the new functionality developed.

All these tests except Unit testing are done in Integration client .

Reward points if it helps.

Former Member
0 Kudos

Hi,

Unit testing is done in bit and pieces. Like e.g. in SD standard order cycle; we do have 1-create order, then 2-delivery, then 3-transfer order, then 4-PGI and then 5-Invoice. So we will be testing 1,2,3,4 and 5 seperately alone one by one using test cases and test data. We will not be looking and checking/testing any integration between order and delivery; delivery and TO; TO and PGI and then invoice. Unit testing is most likely to be done in Sandbox or QAS server, as development client is Golden Client only with Configuration Data & Transaction should be avoided on the same.

Whrereas System testing you will be testing the full cycle with it's integration, and you will be testing using test cases which give a full cyclic test from order to invoice. Similarly, Integration Testing is also most likely to be done in Sandbox or QAS server.

User Acceptance Testing: Refers to Customer testing. The UAT will be performed through the execution of predefined business scenarios, which combine various business processes. The user test model is comprised of a sub-set of system integration test cases. Similarly, Integration Testing is also most likely to be done in Sandbox or QAS server.

Regards,

Rajesh Banka