on 06-20-2007 6:20 AM
Dear All
Where I want to assign quantity of a manpower involved for a particular activity in CJ20N please help me regarding this query its very urgent
Regards&Thanks
P.Srinivasan
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinivasan
You will have to create the activity VIA transaction <b>KL01</b> (Ex: SETUP ), then you maintain that activity via transaction <b>KP26</b> ( assign prices for setup for 1 hour or according to your requiremnet). Then you will have to define this in work center, i mean you can use setup activity and can set the time according to scenario.
Summary (EXAMPLE)
(Cost center, Activity type start and end date should be same, ex use 01012007 - 31122007 in both, this is just an example)
KS01 --> Create Cost center
KL01 -> Create " setup "
KP26 --> Maintain activity "Setup" --> 10 EUR / HOUR
(Prerequistes required: "Cost Center", "Activity Type")
CR01 --> Create Work Center
In schduling tab here, you can define capacity category as 002
Click on capacity button --> here you can plan or define strat & finish time, Break time, Capacity uitilization, No of indv units (Nos of persons req / man power) and so on.
<b> Helpfull: Reward Points </b>
Thanks and Kind Regards
-
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai Srinivas
To assign the Manpower to a particular Activity - first the manpower to be assigned to a workcenter. To assign the Manpower - need to create a workcenter -assuming u know how to create a workcenter - while creating the workcenter - assign the manpower in the capacity category - ex: choose the person category - 002 - double click on the person category which will take u another screen where u will be assigning the working hours -number of capacity - in that screen u can see the HRMS link - click on that which will take to HR integration screen - here u can assign the manpower as persons /positions /required profile). u can assign as many persons u want which will not restrict to the no.of.individual persons.
save this workcenter.
Assign the workcenter in the activity - while assigning - u can see -Personal Assignnment tab will appear - in this u can assign the Manpower indivudally their alloted working hours.
Hope this clear and Award points.
Regards
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.