Dear all,

Can we ensure that the closed projects' info does not reflect while executing Tcode DP95. Projects which are closed in 2001-2002 are also refelcting in this report.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member219195
Participant
0 Kudos

Resolved

Former Member
0 Kudos

Hi Madhusudan

Hope you will not mind to share your experiences to resolve the issue for our benefit.

Thanks in advance.

Enjoy SAP.....

Regards

Sudhakar

former_member219195
Participant
0 Kudos

Hi Sudhakar,

logically, Closed projects should not get executed for DP95.

It was an ABAP error. Actually system is executing open projects while executing DP95 but only was displaying error of closed projects. When I sat with the user and understood the problem, user is giving range for the projects, some of them are closed, so system is giving error for the closed projects. open projects are only executed but system is giving error message for the closed projects which is not required. So found out that there is an error in Abap which our programmer has corrected.

The problem was user was unable to explain on mail/phone. when I personally sat with her, found out the problem.