on 06-19-2007 7:08 AM
dear gurus
pls provide the milestone billing configuration screen shots to my email id raju_varma55@yahoo.com so that i can congigure in my client place
This can be configured using Milestone Billing.
1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
2. Assign New Sales Document Type to Sales Area, For Eg:
1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
Maintain as under (others remaining same)
Billing Relevance: I
Billing Plan Type: 01
IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
Sales Document Type | Item Category Group | Default Item Category
ZOR | NORM | ZTAN
ZOR | DEIN | ZTAD
ZOR | BANS | ZTAS
IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
Note: In the above Billing Type '01' plays the main controller for milestone billing. In Sales order, at item level, we require to maintain the billing plan.
Follow the Sales cycle as normal sales cycle for particular Scenarios
Regards,
Rajesh Banka
Reward point if Helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
<b>Milestone Billing:</b>
This is actual billing, which is done on completion of an activity or difined milestone. This will create accounting entries & is an factual invoice. This is an scenario itself in SD.
1. To create mile stone billing. You need to have a sales order.
After craeting project and mile stone you need to go to sales order and assign the WBS in account assignment. It will prompt if you want to copy the mile stone from the WBS. Then copy the
mile stone from project to sales order. On confrmation i.e. enter finish date in project milestone the
mile stone in sales order automatically get due for billing (billing block is removed) Do billing with respect to salesorder. In you case try to configure the quoataion to billing plan an see if billing can be done.
REWARD IF THIS HELPS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
for milestone billing, you must be able to enter data to identify the
individual milestones.
IMG configuration requires :-
1. Maintain billing plan types for milestone billing in OVBO.
2. Define date description in SM30 - V_TVTB.
3. Maintain Date Category for Billing Plan Type IN OVBJ.
4. Allocate date category in SM30 - V_TFPLA_TY.
5. Maintain date proposal for Billing Plan Type in OVBM.
6. Assign Billing Plan Type to Sales Documents Type in OVBP.
7. Assign Billing Plan Type to Item Categories in OVBR.
8. Define rules for determining the date in OVBS.
Reward points if found valuable.
Thanks & Regards
Subodh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.