on 06-15-2007 3:59 PM
Can someone advise how to split weekly planned order coming from APO into equal daily process orders.
John.
Hi,
Lot size splitting (FS) and in the takht time enter the number of in house production days (1). In the rounding value assign the quantity for the daily lot size.
Planned order will be splitted in equesl numbers in day for the quantity. Now you can convert into process orders.
Regards
TAJUDDIN