Dispatch of BOM Material (Urgent)

Former Member
0 Kudos

Hi,

I have scenarios, i am producing a material Computer having assemblies of CPU, Mouse, Keypad. When confirming production confirming as Computer and the stock is created as Computer. The same i require to dispach on stock transfer scenario from Plant A, here when i dispatch that time dispatch as Computer because computer is relevent for RG1 register in Excise rules and also computer is relevent for billing. After i dispach i need to receive in another plant B at assembly level because assebling is not happening in plant A.

It means i am dispatch in Plant A as Computer and receiving in Plant B as CPU, Mouse, Key Pad.

Can help how to map this.

Regards

Gautam

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As far as I understand, you can only receive what you send. Since you are not ACTUALLY sending the computer (it is not yet assembled), but only sending the parts, you should then dispatch only the parts. There might be ways to solve the problem, but the process doesn't sound right.

Regards

Nikhilesh