Can anyone help me to get Work Breakdown Structure for MDM Implementation? I am looking for detail level activity list.
Thanks in Advance.
Mehul Shah, PMP
Hi Mehul,
SAP follows ASAP Methodology,
 Project Preparation Strategic Planning
 Business Blueprint Requirement Gathering
 Realization Development & Testing
 Final Preparation
 Go Live & Support
Detail Levels are as given below
Blue Print :
1. Define Requirements based on Catalog & Data Analysis
2. Define/Design Repository Schema /Data Model.
3. Workflow Processes
4. Web development Design.
5. Security
6. System Management Strategy
7. Taxonomy Analysis
8. Master Data Consolidation & Harmonization Analysis
9. Print Publishing Analysis.
Regards
Rehman
Reward Points If useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to
https://websmp107.sap-ag.de/support
Search for
MDM 5.5 Implementation Plan.mpp
In the search results click the Documents tab.
This Project plan might give you a better idea.It contains list of activity....
-R.n
Please mark helpful answers......
User | Count |
---|---|
80 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
6 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.