Hi,
In project systems, While confirming the Network with personnel number, the planned cost is calculating based on Activity rate maintained in KP26. However for actual costs, the calculation is from HR I assume. Am I right?
If it is from HR, where in HR the time sheet rate is maintained for the personnel number?
Thanks,
Prabha
Dear Prabha,
Check infotype - .0315.
Also, check the entries of table 'CATSPS' or CATSPM in SE11/SE16.
Hope this will help.
Regards,
Naveen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I got the answer.
FYI
If the network confirmation is entered with the personnel number, the system is looking for the "Position" in HR master and based on that it is picking the workcenter assigned with this resource. So the cost is from the activity assigned in the workcenter even though the network is confimed with a different work center.
Thanks for your responses, it helped me in tracing out this issue.
Regards,
Prabha
\