I Have a Requirement While Picking of the stock,priority basis now thay want change the priority.

Any Bady Can Tell me How to change the Priority while picking stock.

Thanks

Sriram

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

pls check the with "picking requirements" here u can maintain routines based on your individual requirement.

path : logistic excution -> shipping -> picking -> picking requriements.

and second option is picking location determination with situation, for this with all the combination u can maintain logic for the differrent materials based your requriement.