on 06-14-2007 5:31 AM
How much mandays does it take to implement, "Test Equipment Management" under Quality Management module -- for one site - a process industry
It depends on the type of buisiness process.
For normal manufacturing industry, it'll take around 2-3 Weeks. ( Only for QM module).
It includes all master data creation like MIC's, Catalogues with Codes, Code groups and selected sets , Usage Decisions.( As per Cleints requirements)
I assume that all other configurations in PM module is done. Like: Equipment Masters, strategies, Task Lists, maintenance plans etc.
Regards,
Manjunatha G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Sorry for the delay.
In this case, to implement whole of QM and PM, it would take minimun of,
( for One Module)
15 days for Project Map preperation
15 days for Buisiness Blue Print( As is & To be mapping)
45 days for collection of Master Data and simultanious upload in to Test client.
15 Days for testing all processes and link betn. other modules-
15 days for cleaning of datas.
After every thing is well & good, according to SLA, then finally GOLIVE and SUPPORT.
Approximately, 4-5 months for One module..
Hope this helps.
Regards,
Manjunatha G
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.