External requirement transfer other than Account assignment K

Former Member
0 Kudos

Dear Friends,

We are working on sourcing cycle where External requirement is transferred from ECC to SRM.

We have defined various account assignments like NET, OR, AS and assigned attribute in organization structure.

Now if we transfer PR with account assignment "F - order (any thing other than "K - Cost Center") from ECC to SRM then system creates Shopping cart only with account assignment "K - Cost Center". Isn’t it strange behavior?

Has any one faced this problem before?

Does it mean only external requirements with account assignment "K" can be transferred to SRM for sourcing? As in Bid Invitation item detail there is no Account assignment tab to enter the account assignment details.

I even tried removing Account assignment "CC" from organization structure attribute; still system creates SC with account assignment "CC".

Is it standard behavior or is their any configuration?

Regards,

Sandeep Parab

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

I have read it some where. This is standard behaviour. Or might be some missing configuration, as well.

Meanwhile, please go through the following SAP OSS Notes ->

Note 733463 - Conversion of field values w/ blank e.g. account assignment

Note 815849 - FAQ: Account assignment system response

Note 742682 - Entry in EPRTRANS despite item w/o account assignment

Note 618434 - Error in account assignment after external reqments transfer

Note 689138 - Duplicate acct assignment lines after update of requirement

Note 521458 - Sourcing for external requirements

Related Notes

594857 - Sourcing incorrect when vendor preset

588427 - Contract price not transferred for ext. requirements

521061 - Error with sourcing in background with external vendors

505030 - Restrictions for the integration of external requirements

Hope this will help.

Regards

- Atul

Former Member
0 Kudos

Thanks Atul,

I have gone through each of the listed OSS note … but non of them describes about External Requirement transfer other than Account assignment K…

Anyway I have raised this issue to SAP... I shall keep this thread posted.

Regards,

Sandeep

Former Member
0 Kudos

Thanks Friends,

I have received confirmation from SAP and its a limitation that standard SAP supports only account assignment "K-Cost Center" when PR is transferred from ECC to SRM.

Further, if you have a clear rule how to determine the SRM internal acc.ass.cat. (e.g. depending on product categories or products) this has to be developed using Badi's

You can use BBP_ACCCAT_MAP_IMP during import of R/3 Backend documents

and BP_ACCCAT_MAP_EXP during export to R/3 Backend documents.

Please note, that the BADI BBP_ACCCAT_MAP_IMP might not be filled with

acc assignmt type from the backend, but with the values of the used accounting data (e.g. wbs element number) and the already determined SRM category (e.g. CC).

Regards,

Sandeep Parab

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

See if the foll note helps:

Note 505030 - Restrictions for the integration of external requirements

BR,

Disha.

Pls reward points for useful answers.

Former Member
0 Kudos

Thanks Disha,

SAP Note 505030 says "External requirements with an unknown account assignment category are not supported".. but it do not mention any thing about other account assignments other than K-Cost Center like A - Asset, N - Network, F - Order .

Can any one try this simple scenario in their environment and let me know whether it’s a limitation in SRM?

Regards,

Sandeep

Former Member
0 Kudos

Sandeep Parab,

maintain the account assignment category in PPOMA_BBP as order.