Usage of Remaining Duration field (AFRUD-ODAUR) in CN25

Former Member
0 Kudos

Hi,

Appreciate if anybody could tell me whether the field is an input field or its an Calculated field (Duration - Actual Duration).

Thnx & rgds,

Zuaini

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Actual duration and remaining duration both are user entry field. SAP will propose based on the data entered at the time of creation, but both can be changed at the time of completion confirmation.

Enjoy SAP…

Don’t forget to give points if its useful ans.

Namskar

Ketan Dave

Former Member
0 Kudos

Hi Ketan,

Sorry ..... but if i may ask you a bit more:

- unlike remaining works, seems that i have to do manual calculation in order to get the remaining duration value

- is there any particular reason why it behaves this way

Thanks for the input.