Hi. I want to plan safety stock in APO using Advanced Safety Stock Planning. Can someone share a tested scenario/Configuration for this with an example ?
Wanted to understand the logic of getting the safety stock number. If anyone has done a detailed analysis?
Regards,
Bhavesh
Hi Bhavesh
Do you know the source of Supply and Demand variability data that is needed for the input?
which version of SCM are you on? (you have some additional functionalities through safety profile in 5.0)
Do you know which extended planning method you want to use?
Just to add something you might know:-
The two basic parameters is
a)Target Service levels (Alpha and Beta)
b) Replenishment Method (Reorder point or Reorder Cycle)
the combination leads to AS, BS, BT and AT as the four methods
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Harish,
Yes i have the basic idea of the Safety Stock Methods, demand variability, RLT etc. Just wanted to understand the statistics behind the formula. Would you be having an example so as, i can verify the SS which SAP is generating. Or does SAP has any example to which i can verify the same.
Many Thanks,
Bhavesh