on 06-12-2007 3:09 AM
When I do a PGI, I get the following error
E VL 608
Delivery has not yet been completely processed by WM
E VL 605
The batches are not defined for delivery item 000010
Thanks
Hi Gita,
Both the errors occur because the materials that are to be shipped have not been picked. Since the batch is known only AFTER the material is picked (in your case), the batch field is also empty.
To solve the problem, all you have to do is create and confirm a transfer order via LT03 with reference to the delivery.
Regards
Nikhilesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1 . Batches were not defined for the item, Batch management was marked for the item in the material master, but batch determination was not done for that particular item
2. Delivery was not been picked away totally thru Stock transport order, please do picking thru LT03.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi ,
please check the possible delivery date of the materials ( u can see them in shipping details of the sales order. )
thanks
madhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.