Hi Guru's

We are currently doing some testing in Sales Order creation and suddenly a dialogue box is appearing when we change the <b>Requested Delivery Date</b> and <b>First Date</b> fields to the current date.

<b>The Message Reads</b> :

Planned delivery dates exist for the customer.

The requested delivery date is not a planned date.

Select a requested delivery date.

11.06.2007 Current Requested Delivery Date

12.06.2007 Next Planned Delivery Date

Please can you advise how it would be possible to switch this message off.

Thanks in advance for your assistance.

Thks

KC

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

So far as I understand your question I would suggest that you check the Sales Order type definition? In the Sales Order customizing you can define the Plan delivery data or set as proposal de current date…

I hope that hepls you,

Sandra

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi

Check the customer master profile for the calender selected in the unloading points tab. What I understand is that you are forcing a requested delivery date which is out of the calender date as given by customer master.

Thanks

Nikhil

Former Member
0 Kudos

Hi Nikhil

Thnak you very much for your reply .

You are correct it is the delivery dates set on Master Data under the Additional DSD Data button that influences this message.

Do you perhaps know how to turn this warning message of.