on 06-11-2007 5:38 AM
without maintaining MRP Screens in Material master can we perform availability check for a material ? if YES ,can somebody pls explain me how can we perform .b'coz my client is not manufacturing material instead he is procuring from vendor .
hi,
without MRP you cannot run availability check.
thanks
Sadhu Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In Material Master, Maintain Availability Check Field in Sales: General / Plant Tab page, instead of MRP views.
Regards,
Rajesh Banka
reward points if helpful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi shailesh,
its not possible to do availabity check with out MRP screens..as we have to specify the check group/rule.. if ur cleint in getting stocks also no issuesyou can maintian the MRP screens...
if any doubts pls get back..
ramki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think it is possible. We will maintain the Checking group in the Sales general plant at Avaialbility check. Availabilty check control is present at the Requirement Type.
Based on the MRP group or MRP Type, Requirement type is detrmined in the sales document. If we dont maintain these in the MRP Screens, Requirement Type is found out based on the material Type. Based on the requirement type Requirement class is determined where there are controls for Avaialbility check and Transfer of Requirements.
If any doubt please let me know
Regards,
Sree
Message was edited by:
sree s
Message was edited by:
sree s
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i think it is not possible because the field i.e checking group which most important in availablity chek is there in MRP3 view of material master and if it not implemented then it is hardly possible to do availabilty check as checking group and checking rule are important for the same .
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
With out maintaining the MRP 3 VIEW you can't do availability check.
The checking group defined as 01 and 02 is the starting point for availability check.This checking group is assigned in MRP 3 view in the availability check
field.
Regards,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.