Subrequirements for component codes not interfaced from R3 to APO

Former Member
0 Kudos

Hi experts,

Could you pleas help me out? In R/3 we have Parent codes and the demand for these parent codes are translated into SubReqs in the component codes. SubReqs are successfully interfaced to APO via CIF. However, when the SubReqs for the component codes are generated from confirmed scheduling agreement in the parent codes, the SubReq no longer appear in APO (e.g. planning book or product view).

How do we get those elements interfaced to APO? All materials, schduling agreement document numbers and vendors are active in CIF models.

Thanks!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Edgar.

Try this thread.

Hope this helps.

Mark

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Edgar,

Try to delete the demand at the parent code level in APO and run delta report.

Former Member
0 Kudos

Hi Lito!

How are you? haha thanks for still helping out with APO.

We've tried that before and it worked, however the subreqs attribute to the firmed SA's were gone again the next day. It's really wierd since only such Subreqs get deleted while ordinary Subreqs (e.g. generated from forecast for parent codes) remain in the planning book.