Error PO transfer

Former Member
0 Kudos

Hello experts

I am in SRM 5.0 I have configurated the ECS and when my shopping carts are aproved and converted in POs in SRM an error occur whem this PO are tranfered to backend

Order 4000000004: Order unit PC cannot be converted into base unit P C

I checked transaction CUNI and entries are the same in backend.

Some idea to help me?

Thanks

Nilson

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Which R/3 and SRM versions are you uisng ? Seems to be a bug. Problem can happen at either of the systems.

<u>Please go through the following SAP OSS Notes, which will help -></u>

Note 523496 - FAQ: Alternative units of measure

Note 688365 - ECS: Incorrect purchase order price unit in backend PO

Note 910391 - Shopping cart: Data loss due to old BBP_CREATE_PO_BACK BADI

Note 207075 - ME21N/ME22N: Conversion problem purchase order qty

Note 932236 - BAPI_PO_CREATE1: Purchase order price unit not transferred

Note 990692 - Error with Price Unit in purchase orders

Note 573493 - ECS: Error for SC item without plants

Note 1008081 - Can't change UOM in process PO transaction BBP_POC

Note 942531 - Price units in purchase order and invoice do not match

Note 514459 - Shopping cart => backend requis.: no UoM conversion

Do let me know.

Regards

- Atul

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Pls refer the foll threads:

BR,

Disha.

Pls reward points for useful answers.

yann_bouillut
Active Contributor
0 Kudos

Hi,

You have an issue with UOM.

- Do you have any SAP material master ID in your PO ?

- PC and P C : if you did a copy and paste, you have a blank between P and C: please check your config

Kind regards,

Yann

Former Member
0 Kudos

Hi Yann

The mentioned error occur with material that comes from a sap material master.

I checked the UOMs in SRM and backend and it's have the same configuration.

Is it transfered from R/3 object DNL_CUST_BASIS3?

I create entries manualy and after runing this objectm what's the correct way?

I am in SRM 5.0 ECS.

tHANKS

Nilson

former_member293881
Participant
0 Kudos

Hi Nelson,

Please check SRM PO UOM. ( e.g. PC). Now in backend, check Base UOM of that material. If it is different than SRM PO UOM, then you need to maintain alternative UOM with conversion of that material.

I think that will resolve the issue.

Regards,

Rahul Mandale

Former Member
0 Kudos

Hi Rahul

I compared the UOMs and nothing diferent and the problem is occuring for all materials, how can I see the datas that the SRM send to R/3 is in BBP_PD?

What is table there?

Thanks

Nilson

Former Member
0 Kudos

Hi

Please check whether OSS note 797224 is implemented in your R3 backend. If yes, due to this you will the mentioned error as you said. Try to implement the OSS note 848242 in R3 backend, which is the corrective note for 797224.

Note 797224 - Transferring own conversion factors from SRM (DLA solution)

Note 848242 - You cannot convert units of measure due to Note 797224

Table to look is BBP_PDIGP in BBP_PD.

Rgds

Reddy