Maintain a material consumption -> alternative component

Former Member
0 Kudos

I have been trying to enter a component in the PPM for the activities i have defined but then it is giving me the following error

Maintain a material consumption -> alternative component. Can anyone explain to me the solution to this error.

Maintain a material consumption -> alternative component

Message no. /SAPAPO/PPM_MAINTAIN150

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

THank you for the solution

Former Member
0 Kudos

Hi

Pls enter the qty against the component in the PPM. It's basically the consumption.

Hope this helps

regards

Vijay

Former Member
0 Kudos

Hi Suresh.

You need to enter the amount to be consumed/produced. Where you entered the component you have to fill in the fields Unit of Measure and either Variable or Fixed Consumption (Variable is the more common, fixed is normally used for input components where the amount used in an order is the same no matter how many are produced)

For basic scenarios:

- If it is the output component then the variable consumption quantity is the amount that the rest of the PPM data will reference.

- If it is an input component, then the variable consumption quantity is the amount required to produce the variable consumption quantity of the output component

Hope this helps, Mark