on 06-05-2007 7:00 AM
Dear All
Can anyone explain me,what are all the configuration i have to do it in PS IMG for billing a project
Regards&Thanks
P.Srinivasan
not solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinivas
Besides RRB, we have another type of Billing procedure that is MST billing (Milestone Related Billing). In this scenario Project WBS elements are linked with SD Order line items. Plese go through the following to enable to you to understand and prepare settings accordingly.
A. Billing Plans for WBS elements
A.1 Maintaining Billing Plans for WBS elements
A.2 Generating Dates from Milestones
Furnishing below the link which would be of helpful to you.
http://help.sap.com/saphelp_47x200/helpdata/en/4c/22744246e611d189470000e829fbbd/content.htm
Enjoy SAP....
Regards
Sudhakar
PS: Pl reward points for suitable solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you are using resource related billing,then you need to maintain DIP Profile.
Please follow the path as below.
Project system-Revenues & Earnings-Integration with SD documents-Creating Quotations & Project Billing-Maintain profiles for Quotations & Billing
For more info please visit following link.
http://help.sap.com/saphelp_46c/helpdata/en/aa/96853478616434e10000009b38f83b/frameset.htm
Regards
Tushar
PS: Reward points if answer is useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.