on 06-01-2007 10:09 AM
Hi,
We are on ECC6 with SAP_BASIS HP10.
We would like to go to HP12 for extra functionalities but our CRM environment is on SAP_BASIS HP10.
Our system administrator says that the HP level in the different environments
has to be equal.
This seems to me very strange because HP's are mostly bug fixes so what could be the relation between the CRM level and the ECC level?
Thanks for any help,
Hans
Hi,
It could be. All depends on the prerequisites of that package.
Our system guys advice not to go for the packages though but for the stacks, where all dependencies are taken care for and checked by SAP.
All info on stack/packages dependencies can be found at service.sap.com/swdc where you also download them.
Eddy
-
PS. Which type of SDN Ubergeek/BPX suit are <a href="/people/eddy.declercq/blog/2007/05/14/which-type-of-sdn-ubergeekbpx-suit-are-you">you</a>?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.