cancel
Showing results for 
Search instead for 
Did you mean: 

Remove a component from PDS

Former Member
0 Kudos

Hi Everyone,

I have a PP/DS - PDS for material A, inputs are materials B and C.

I decide that I will not plan material B in APO anymore, but it will still exist in R/3 BOM of material A. How can I achieve this?

I set the MRP type of B to PD, instead of X0. And then I run transaction CURTO_CREATE_BOM in SAP (PDS only includes BOM, not routing, since it is a phantom assembly). However, I receive message "No BOMs found for the selection criteria", since I haven't changed anything in BOM of material A, I guess.

Is there a way to do it?

Thanks in advance,

Ergul

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ergul

Pls delete the particular material in APO also

Hope this helps

regards

Vijay

Former Member
0 Kudos

Yes, I should try this way.

Thanks again,

<i><b>Ergul</b></i>

null

Former Member
0 Kudos

One note:

Deleting PDS and then retransferring it can be used for this purpose, but in order to delete a PDS, all orders for the material (for phantom assembly, orders of the upper level of phantom) must be deleted which is not good. So we must find another way.

Thanks,

<b><i>Ergul</i></b>

Former Member
0 Kudos

i assume all your orders are sent to R3 too

If so, You can do the following

temporarily stop all activity in bothg system,

make inactive the CIF integration models for these orders.

Delete the orders in APO,

Delete or change your PDS,

Restart the Integration models

Do a CCR and the orders in APO and R3 will be reconciled

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Harish,

Can u tell me the detailed abbrevation for CCR