on 05-31-2007 11:52 AM
Dear All,
we use a dynamic procedure for inspection lot. We use a dynamic modification at characteristic level.
The system does not change the quality level when we valuate the single characteristic (in transaction QE51N) but change the next quality level when we insert the usage decision (transaction QA11).
Is it normal or we can set different options in the dynamic sample procedure (QDV1), sampling scheme or dynamic modification rules?
thanks for your cooperation
regards
matteo
Hi,
Usually DMR is used at lot level.
So better to evaluate at the lot level.
Also can come clear on what is your requirement so that i can try to help.
regards
Ananth Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
<b>Hi,
thanks for you interest.
Below you could see sap reply to my question:</b>
I'm afraid that is not an error but a wanted behaviour.
The quality level is a data record that the system automatically
updates at the time of
-> Inspection lot creation
-> Usage Decision
This means, it's not possible to change it in QE51N.
Regarding your last question : the quality level is updated
during sample determination.
I'm afraid that your requirement is not in the standard system.
<b>So, I suppose you can't help me more
Thanks
matteo</b>
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.