Hi All,
I have a delivery document with batch, but when i want to change the delivery quantity, i have to change first the batch quantity then change the delivery quantity on the Schedule line item level.
Is there any way to make this automatic? I mean when i change the delivery quantity, Automatic change the batch quantity.
Thx
HI Ahmed.,
Try out this use exit MV50AFZZ,This may work out
Thanks & Regards
Narayana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
my name is Antonio and I have the same problem.
Has you fixed the problem?
Would you mind give me some clue, please?
Thx,
Antonio.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to use user exits in MV50AFZZ or MV50AFZ2 for program SAPMV50A.
Form USEREXIT_BATCH_QUAN_ALLOCATION .
Reward points !!!!!!!!!!!!!!!!!!!!!!
Thanks,
Kamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.