Projects created using Cproject does not allow WBS milestone to be created

Former Member
0 Kudos

I am trying to create a project in the ECC system through Multi Level Controlling with Automatic Transfer from cprojects to ECC.

After I create a PS project, I would like to manually add muilestone for the PS project either in ECC or Cprojects (using service in accounting view). In both the case I am geting error saying

"No authorization for Create Milestone"

Message no. CNPB009

Can anybody help me resolve this issue.

Best Regards,

Joseph.

Accepted Solutions (0)

Answers (1)

Answers (1)

schneidertho
Advisor
Advisor
0 Kudos

hi joseph,

try transaction SU53 to see the failed authorization check. i don't think that this is directly related to multi level controlling.

cheers

thorsten