on 05-27-2007 9:32 PM
Hi
I have crm 5.0 dev and qa system installed. I need to setup CHARM for transports.
I read about creating a maintenance project and maitenace cycle for this.
I have following questions:
1. Do I first need to set up a normal STMS between dev and qa systems even before going for CHARM ?
2.Is there any step by step guide to setup charm
Regards
Shankar
Hi Srihari,
If you have to set up CHARM then you first have to set up TMS between dev and qas server only then your change request will be transported to the required server.
For further documents please go to the following link.
service.sap.com/rkt-solman
there are various useful documents and tutors which will help you out in setting up CHARM step by step.
also check the ppt,
http://service.sap.com/solutionmanager
Goto Media Library --> Use Case Presentations --> SAP Solution Manager - Change Request Management
Hope this will help you out, do rewards point if found useful.
Thanks
Manas
Message was edited by:
Manas Srivastava
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Manas
Thanks for reply
Yes I have set up a normal STMS and configuring chnage management as per SPRO. When I run tmwflow/csmconf I see only two tabs "system change option" and "critical objects" I dnot see "distribute routes" " general settings" and "project structure" tab. Shall appreciate your reply.
Regards
User | Count |
---|---|
88 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.