on 05-25-2007 3:01 PM
Hello All,
I want to define interoperation time relationships for PP/DS-PDS operations.
In R/3, I have a routing with 2 operations. I defined maximum wait time of 10 minutes for operation 10. I transfer PDS to APO. I cannot see this 10 minutes anywhere on PDS. What I see on PDS Activity relationship tab are three columns;
- preceding activity
- succeeding activity
- material flow
I cannot see any min.interval, max.interval column for PP/DS PDS. I can see these columns in SNP-PDS,but the data I entered on R/3 routing is not transferred to this field. Also I cannot maintain as PDS cannot be changed in APO.
How can I maintain activity relationships on PP/DS-PDS?
Thanks in advance,
<b><i>Ergul</i></b>
You define parallel sequence in R/3 routing.
But remember, this only works for PP/DS PDS's.
Ken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That is true... ONly for PP/DS PDS.
Are you not seeing them in a PP/DS PDS?
Ken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No, I cannot see them in PP/DS PDS.
Actually what I want to do is to define start-start relationships between operations in a PDS. I cannot see any parameter for this on PDS. But I see the parameter (Constraint Ref. Type) on an operation on planned orders. However, this parameter's value is "End-Start Relationship". I want to make it "Start-Start relationship". How can I do this?
Thanks
Any comments?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.