on 05-25-2007 2:34 PM
Hello everybody,
We are on SRM4.0 and have implemented plan driven procurement (we are using only the bidding, contract and PO functionality). When we do a GR (for the complete PO qty) in the backend the Delivery Complete indicator is being set in the R3 system. However the final_entry indicator in the SRM PO is not being set. How is the final_entry indicator set in SRM PO?
Thanks in advance for your help.
Venkat
Hi
<b>Please go through the following SAP OSS Notes as well -></b>
<u>Note 1031298 No change in final entry flag after cancel/return delivery
Note 1040658 Inward delivery completed ind. in item detail screen of WE
Note 872011 Return not possible for item with final_entry set
Note 895171 Unsynchronized follow-on document indicator in extended PO
Note 785144 Display of closed purchase order items in goods receipt
661912 Short dump CONVT_NO_NUMBER when changing purchase order
617392 Inward delivery completed ID is not set in purchase order
831448 BBPPO01:Final invoice indicator is not reflected to Backend
810675 ECS: Inward delivery compl/final invoice ind not displayed
757201 BBP_ENTRYSHEET_CREATE_40B: Interface enhancement
632042 Cancel delivery completed indicator in purchase order
Note 502132 GR:"Delivry completd" indictr after retrn delivry and deletn</u>
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Check the following notes:
Note 763980 - ECS: Reading values from the R/3 Logistics back end (I think this will work, as we faced similar issue)
Note 895171 - Unsynchronized follow-on document indicator in extended PO
Rgds
Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.