please let me know the the below answer?

is Order Date Promised where can we find?

is some thing equal to availability date or conformed date or is it different?

pl let me know the sameIf it is different .

Thanks&reagrds

Sumanth.E

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Arun,

The system determines the availability of materials according to the ATP method (availability-to-promise). Using this method, the system checks

  • Whether the material requirements can be covered on the requirements date

  • At what point in time the requirements can be covered, if a full coverage of the requirements is not possible on the requirements date.

the date promised...~ ATP

If an overall check determines that a material is not available on the required date, the system activates the status "material shortfall" in the order header.