on 05-24-2007 3:51 PM
Hello,
I have scenario from R\3 to BW
When I try to export the scenario to the xi production environment I have a problem-
In the design part is work Ok
In directory part I have a problem.
The .tpz file crate with BW dev system and I cannot succeed importing the .tpz file to xi production environment.
I received the follwing message:
Business system BWD100 is not assigned a business system in group XI_PRD
Any advice?
Regards
Elad
But, if you want to use another Business system Name in production.
in that case, create the new Business system and the realted integration server for this would be the production integration server and then go to the Dev / QA Business system that has to be replaced with this Business System , chosee Transports and assign the new Business System as the Target Business System.
Now when importing the TPZ file the business system name will point to the production business system as needed.
Regards
Bhavesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Elad,
If you do not want to change the name of the Business System in your production box , then this is simple.
Go the SLD. Go to your Business System , "BWD100" and in the option <b>Related Integration Server</b> select the XI Production Integraion Server.
Now, if you import the import will be successful.
Regards
Bhavesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
9 | |
9 | |
6 | |
6 | |
6 | |
5 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.