we can create the project definitons,WBS elements,Network in CJ20N and in CJ27.What is differnce between this two transactions
Regards&Thanks
P.Srinivasan
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinivasan,
In PS , there are two major Tools from where you can create your project structure. One is Project Builder ( CJ20N) and the other is Project Planning board.( CJ27).
Project Builder is primarily used while creating and maintaining a project structure i.e Project definition , WBSE and network activities.
Project planning board is very useful if you are working with dates / scheduling / Capacity planning in the network / attaching maintenace orders etc.
The major difference between the two is that you can view and customize Gantt chart only in PPB . Also Capacity planning can only be done in PPB.
I hope this explanation helps. Addtionally follow the link ( ECC 6.0 )
http://help.sap.com/saphelp_erp2005vp/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm
Warm regards,
Srinivas Potluri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
CJ27 is specific for Creating a Project i.e." CJ27 is Create Project" but whereas CJ20N is a Project Builder where you can see clusters of projects and activate any one with almost all the details and levels of the projects.
Regards
Rehman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.