Hi XI gurus,

I know that time based scheduling for adaptors(Let say polling starts at 2 AM daily) can be done in SP19 of NW2004.

Could anyone tell me in NW2004S this feature is availbale or not and if yes on which SP ?

Regards

Vijay

Accepted Solutions (1)

Accepted Solutions (1)

bhavesh_kantilal
Active Contributor
0 Kudos

It is on SP 10 on PI 7.0 , i.e NW2004s

Regards

Bhavesh

swatantra_vijay3
Participant
0 Kudos

Wow!!!

Thanks Bhavesh,

Now i have Oracle DB with SAP Interafce . It will be JDBC ->RFC(Sync)->JDBC

Do i really required BPM we are on PI 7.0 SP11

Thanks in advance

Regards

Vijay

bhavesh_kantilal
Active Contributor
0 Kudos

No BPM Needed.

Look into this thread and check things out.

I implemented a File - RFC - File. But this holds truw also for a JDBC - RFC - JDBC.

Regards

Bhavesh

Answers (1)

Answers (1)

Former Member
0 Kudos

SAP NetWeaver 2004 SP Stack Release to Customer (RTC) Additional nformation

SPS 21 Calender Week 42, 2007 (planned)

SPS 20 May 3rd, 2007

SPS 18 August 22nd, 2006

more detail

https://websmp106.sap-ag.de/~sapidb/011000358700001130682005E

SAP NetWeaver 2004s SP Stack Release to Customer (RTC) Additional Information

SPS 14 Calendar Week 45, 2007 (planned)

SPS 13 Calendar Week 32, 2007 (planned)

SPS 12 Calendar Week 21, 2007 (delayed)

SPS 11 March 5th, 2007

more detail

https://websmp106.sap-ag.de/~sapidb/011000358700004584092005E

hope help you!