Hi Atul,
Rollout :
1.The company might have purchased new plant for which we have to do the necessary things as per the Client requirement.
2.In the Existing company they want to go for new things like( Eg:- EDI Immplementation for a particular plant and sales area)
3.in the Existing company,they might be using some programs for which they dont want to use the same in the coming furture etc.,
the above cases can be called as Roll out.
Like immplementation we dont have any phases in the roll out but we have to complete the rollout as specified date by the client.
Please Reward If Really Helpful,
Thanks and Regards,
Sateesh.Kandula
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
in Roll out project,Generally data migration and end user training takes place,But if a company going for seperate implementation in that area also then again implementationa and all the phases comes in to picture
Reward if helpfull
Thanks & Regards
Narayana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.