Hi

This is a doubt regarding the transports

R/3 CID ---SRM SRD

R/3 CIQ ---SRM SRQ

R/3 CIP ---SRM SRP

When i do configs like creating logical system,should i create in each client in SRM

Also distribution model--I create a distribution model in SRD and distibute it to backend R/3 CID.Should I repeat this procedure for quality and prdn or is it transportable.

Please suggest me if there is any other solution

Regards

J

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Logical system for dev,quality and prod is different.

Did you mean that when I transport it in SRM, SRM quality server will correctly take the R/3 quality server.

Also Distribution model in the dev system I give the dev values.

when I transport it the SRM quality will take the R/3 quality server values

Former Member
0 Kudos

Hi

<u>You need to maintain all the Server definitions in the Development system and then transport the same data to all your other systems.</u>

<b>Note 447651 - Transporting EBP Systems and organisation modell</b>

Hope this will help.

Regards

- Atul

Former Member
0 Kudos

Hi

<b>You can transport the changes to Other clients. This is standard SAP Functionality.</b>

<u>E.g.,

Table View -> Transport entries -> in case of Logical Systems</u>

<b>This thing is available in all the Distribution model as well.</b>

Hope this will help.

Regards