Question about the configuration material price

Former Member
0 Kudos

Dear Expert,

We have a question about the configuartion material price caculation, our sales do not want to use the price caculate from system, they want to use some fix price. And the billing document they want to send to customer not only include the configuation material, they want to send to customer the billing document include the whole price for some standard materials show as standard production, and the speical accessaries price. Do you have any solution?

I will give you bonus point.

Thanks and best regards

Gang

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

What ever the price we maintained internally, I think u can maitain sales price in SO as u wish. my suggestion is that u can discuss with your SD consultant and find out work around solution to ur requirement.

Is this RRB related scenario?.

Regards

Sudhakar

Former Member
0 Kudos

Hi,

the problem is not only price, also the production structure, in the BOM, there is no standard semi-finish goods, and no price for semi-finish goods, but the sales want to show the semi-finish goods with some special parts.

thanks