on 05-21-2007 3:26 PM
Hello,
I am having problem in ECM.
I have created ECR and converted to ECO. I have changed the material revision level from A to B and saved.
I tried to UNDO the changes and it is not being done.
2 nd problem: I have used revision level by mistake i have used D instead of C.
I could not able to use revision level C with same change number.( Because the sequence in customisation A>B>C)
Can any one help me?
Thanks,
Raj
Hi Rajasekhar,
Once when ECR goes to ECO stage (i.e. Order Stage) you can't change anything, as the Request has turned to Order (i.e. ECR to ECO),
So when you have completed the revision level assignment from A to B using the Change Number, it is not Possible to revert back. You cannot Undo the change.
Regards
Rehman
Reward If Useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.